Case studies

Management of the relocation project – DCM Group

DCM Group, to meet the expected growth, has decided to triple its production facility in a new 100 000 sq.ft. building located in St-Bruno de-Montarville.​

ANTICIPATED RESULTS

72 hours

Maximum production downtime by department​

14 days

Total delay to move production and administration

100,000 ​ sq.ft.​

Total building area

Progima supported the DCM Group throughout the relocation project. We designed an optimized layout of both the production and office space. Subsequently, our role was extended to also manage the move in order to minimize the production downtime. ​

The biggest challenge was moving each departement within 72 hours while the building was not yet completed. We ensured a smooth transition while allowing the contractor to finalise the construction.​

"Thanks to their commitment, their agility and their expertise, the Progima team has been able to guide us through the processes in order to reach our objective while respecting our budget and set timeline."


Thomas Langhame, ing.​, Vice President, Engineering and IT​